Work on Khari railway station almost complete

Source – https://www.greaterkashmir.com/chenab-valley/work-on-khari-railway-station-almost-complete

Publisher – Greater Kashmir

Ramban, Oct 13: In a significant development, the work on Khari Railway station on the 111-long Banihal- Katra section of the Udhampur Srinagar Baramulla Rail Link (USBRL) project in Ramban district is almost completed and ready for operation. 

The trolley runs between Banihal and Khari railway stations in Ramban district on the 111-long Banihal- Katra section of the Udhampur Srinagar Baramulla Rail Link (USBRL) project is being conducted as the railway track was successfully laid between Banihal and Khari railway stations in Ramban district was completed.

Earlier in August the first trail run on the 8.6 Km long train tunnel, T-74 and at other important stretches was successfully conducted.Officials said the  track-laying works between Banihal-Khari and Khari-Sumber Railway stations were completed and the trail trolley runs are being conducted by the Engineers and technicians of Northern Railways.They said trolley runs are being conducted from Railway Station Banihal to Railway Station Khari in the presence of senior officers and engineers of Northern Railway and construction company IRCON officials.

They said the work on track, platforms, Railway Station and other allied works are completed. They said only some electrical, exhaust work inside tunnels is pending.They further said track laying work between Summer and Sangaldan stations is going on round the clock and near completion.

Railway officials said the work on residential quarters for Railway Staff and other infrastructure for Railway Stations at Khari, Sumber and Sangaldan is almost completed.  They said work on platforms and the laying of railway tracks connecting Sumber and Sangaldan stations in the Rambam district is in progress.

They said we are working round the clock to finish pending works on three important stations Khari, Sumber and Sangaldan on the Katra-Banihal track in Ramban district. We are expecting that Rail will chug soon on the Katra-Banihal section, they added. Deputy Commissioner Ramban, Mussarat Islam said that the work on Khari Railway Station is near completion. He said it would help in the promotion of tourism in the Mahu Valley of Khari.