35.1 C
Delhi
Saturday, October 5, 2024
spot_img

Latest Posts

Mumbai–Ahmedabad high-speed rail corridor work under progress: Minister of Railways in Parliament

Source: https://newsonair.com/2022/04/06/mumbai-ahmedabad-high-speed-rail-corridor-work-under-progress-minister-of-railways-in-parliament/

Publisher: News On Air

The work on the first High-Speed Rail Corridor between Mumbai and Ahmedabad is in progress with technical and financial assistance from the Government of Japan.

In a written reply in Lok Sabha Minister of Railways, Communication and Electronics and Information Technology Ashwini Vaishnaw said that all statutory clearance relating to wildlife, Coastal Regulation Zone(CRZ) and forest clearance have been obtained.

The Minister further said that out of a total 352-kilometre length of the project located in Gujarat and Dadra and Nagar Haveli, civil works in 352-kilometre length have been started in different phases from December 2020, onwards.

He said the anticipated increase in cost and time can be fully ascertained only after completion of land acquisition, finalization of all contracts and associated timelines

Latest Posts

Don't Miss